SPCC is the abbreviation for the Spill Prevention, Control, and Countermeasure (SPCC) Rule.  An EPA regulator from the Office of Emergency Management (OEM) recently revealed the most common SPCC violations he finds on field inspections.

Typical Violations from All Facility Types…

  1. Container incompatibility. Some examples include using underground storage tanks as aboveground storage tanks and using heating oil tanks to store gasoline. This is a big no-no with the EPA. A good option to prevent this issue is to work with a service that provides control automation systems for oil companies in order to keep track of and monitor this resource.
  2. Containment drain valves left open.
  3. Poor integrity of tanks.
  4. No or inoperative overfill device(s) and/or no inspection of the device(s).
  5. Failure to address facility tanker trucks/refuelers in the SPCC Plan.
  6. Small containers located in buildings that don’t have proper secondary containment. Some facilities think that because a container is in a building it doesn’t need containment, but it does.
  7. Improper maintenance and inspection of containment structures. For example, at one facility the EPA had found that a groundhog chewed through the wall of a tank causing it to leak.
  8. Poor piping support.
  9. Buried piping after August 16, 2002, that has not complied with cathodic projection requirements.
  10. Poor double-wall piping.
  11. Poor drainage in buildings and not doing regular clogged drain cleaning with the help of a professional drain cleaning service.
  12. Not permanently closing containers.

The SPCC Inspection Will Generally Consists of These Activities…

  • Opening conference
  • A discussion of facility operations and site
  • Review of a detailed SPCC checklist
  • On-site review of the facility’s SPCC Plan
  • Review of the facility’s records
  • Facility walk-through
  • Closing conference in which the EPA will give verbal feedback about the findings of the inspection
  • Follow-up letter discussing deficiencies
  • Enforcement (in certain cases)

The EPA will send a notice describing the SPCC deficiencies found on inspection within 45 days of the closing conference, so it’s highly recommended that a facility corrects any issues and sends a letter back to the Agency stating what was corrected.

 

Contact Us (859-689-9222) for a Free Consultation!

About Environmental Risk Management

1-Source Turnkey Environmental & Safety Services

Since 1989, Environmental Risk Management has been providing responsive, client focused 1-source turnkey solutions for a wide variety of environmental safety challenges. With our experience and extensive network of diverse internal and external resources, our clients trust us to provide quality Environmental & Safety Services for their businesses. Our environmental compliance specialists recognize the need to consult with private industry and the business community and our goal is to ensurer our client’s are complying with complex environmental regulations and minimizing their environmental liabilities.